Works Info - Juvisy-sur-Orge - Rue Piver
Published on
To allow the civil engineering work of the T7 tram planned in the lower part of the Parc de la Mairie, the entrance gate to the Park must be removed.
Where?
Rue Piver, at the entrance gate of the Parc de la Mairie de Juvisy-sur-Orge.
When?
The removal of the gate takes place in 3 phases, from October 12 to November 27, 2026, Monday to Friday, between 7 a.m. and 7 p.m.:
• Phase 1 - from 12/10 to 22/10: installation of the site and removal of the iron gates of the gate.
• Phase 2 - from 22/10 to 09/11: removal of the right part of the gate.
• Phase 3 - from 10/11 to 27/11: removal of the left part of the gate.
What does the work involve?
• Removal of the gate of the Parc de la Mairie de Juvisy. The gate will then be restored and reinstalled at the end of the civil engineering work.
What impacts?
For pedestrians:
• Pedestrian paths are maintained.
• Pedestrian access to the Park is maintained during all the works.
• Access to neighbouring homes, shops and car park entrances is maintained.
For the road axis:
• Until the beginning of November, traffic on Rue Piver will be maintained alternately in both directions, then will become one-way in the city centre > RN7 when the civil engineering works are completed.
• Access to the Park by car via the entrance gate is not maintained.
For buses:
• Bus stops are maintained.
We thank you for your understanding and apologize for any inconvenience caused.